How to Prepare a PTFE-Lined Piping Line List

A quotation starts with a tagged line list. Assign each straight length, spool and fitting a unique identifier that also appears on the isometric. State the nominal bore and the mating flange detail on every branch, especially where an existing plant mixes flange systems.

Flange face and lined steel pipe during finishing
Industry context: Flange face and lined steel pipe during finishing

Dimensions and service inputs

Record the overall face-to-face dimension and indicate which faces must be clocked. A loose flange may ease installation, but it does not solve a dimensional mismatch. Provide separate lengths for straight runs and fabricated assemblies.

Bores of large diameter PTFE-lined steel pipe sections
Illustrative product reference: Bores of large diameter PTFE-lined steel pipe sections

Before issuing the RFQ

Add the normal and upset process conditions, insulation boundaries and any vacuum cases. Issue the latest drawing revision alongside the table and ask which line items need clarification before release.

Turn an isometric into a quote table

For a line with two straight pieces, one branch and a removable module, use four independent tags. Record the drawing revision on the table, add a quantity column and list each mating end on its own line. If the module must arrive as a single assembly, say so in the packing and delivery notes.

Discuss your application

Send the medium, operating conditions and mating dimensions for the parts under review. If the project is a replacement, include the existing equipment tag and drawing revision.