Vacuum and Service Transients in Lined Equipment RFQs
Vacuum conditions can arise during cool-down, pump-out, drainage or a control upset. List the cases individually and distinguish actual absolute pressure from gauge pressure.
Dimensions and service inputs
Provide the corresponding wall or process temperatures when known, and explain how long the equipment can see that condition. Changes during washing or standby can differ from the normal production cycle.
Before issuing the RFQ
Ask for a written service envelope for the specific geometry and lining system. A positive pressure figure by itself does not establish vacuum suitability.
Put each transient in a separate row
A simple schedule can include normal operation, drain-down, cool-down and cleaning. Give pressure, temperature, duration and the expected sequence as separate columns. Identify which rows are estimates so the supplier knows what needs verification.
Related products
Related information
- PTFE Sheet-Lined Vessels
- Custom PTFE-Lined Reactors
- PTFE-Lined Steel Pipes
- Request a project quotation
- Technical resources
- Specifying Lined Equipment for Multi-Product Chemical Plants
Discuss your application
Send the medium, operating conditions and mating dimensions for the parts under review. If the project is a replacement, include the existing equipment tag and drawing revision.