Checking Mating Interfaces on Fluoropolymer-Lined Piping

A flange check starts with the mating components. Capture the drilling, bolt circle, flange facing, bore and whether the end is fixed or can rotate.

Flange face and lined steel pipe during finishing
Industry context: Flange face and lined steel pipe during finishing

Dimensions and service inputs

Check how the protruding liner face sits next to the adjoining component. Identify any spacer, gasket or blind in the joint design and confirm the installation method with the equipment supplier.

Lined pipe end and flange detail
Illustrative product reference: Lined pipe end and flange detail

Before issuing the RFQ

Make the flange schedule part of the RFQ. Where an old drawing and the field dimensions differ, identify the discrepancy before manufacturing.

Capture the mismatch before ordering

If a new rotating flange mates with an existing fixed flange, record which bolt positions have to align and what tool clearance is available. For a spacer or blind, specify its thickness separately so the planned pipe length includes it.